Mechanical Specifications
Vibration
MIL-STD-202G,
Method 214A,
Test Condition A
5.35 Grms,
4hr / axis
Must operate per specification during and after the test.
Shock
MIL-STD-202G,
Method 213B,
Test Condition J
30G Peak,
11 ms,
½ Sine Wave
Must operate per specification during and after the test.
Environmental Specifications
Temperature
Cycling
Per SAE J1455, Rev.
JUN2006, Sec. 4.1,
Test 4.1.3.1
Fig. 2B*
Must operate per specification during and after the test.
Thermal shock
Per SAE J1455, Rev.
JUN2006, Sec. 4.1,
Test 4.1.3.2
Fig. 2C*
Must operate per specification after the test.
Humidity
Per SAE J1455, Rev.
JUN2006, Sec. 4.2,
Fig. 4B*
Must operate per specification during and after the test.
Altitude - Operating
Per SAE J1455, Rev.
JUN2006, Sec. 4.9,
Table 2*
Must operate per specification during and after the test.
Altitude – Non-
operating
Per SAE J1455, Rev.
JUN2006, Sec. 4.9,
Table 2*
Must operate per specification after the test.
Electromagnetic Specifications
Conducted
Immunity
Per SAE J1113/3,
Severity Level L6 (0.5W)
Manual restart required for pulses 1, 2b, and 4
Radiated RF
Immunity - Bulk
Current Injection
Per SAE J1113/4,
Class C,
Region 2,
80mA
Immunity to
Radiated RF
Per SAE J1113/25 to
500 MHz
Per SAE J1113/27
500 MHz to
2 GHz
Load Dump
Per SAE J1455, Rev.
JUN2006, Sec. 4.11.2.2.1
Jump Start Test
Per SAE J1455, Rev.
JUN2006, Sec. 4.11.1
24 Vdc Applied to DC
Terminals
The inverter system should restart without a fault.